04/11/2026
NextDecade targets first gas at Rio Grande LNG before year-end

US developer NextDecade plans to introduce first feedgas into its Rio Grande LNG export facility in Texas before the end of 2026 with a view to produce first LNG in the second quarter of 2027, CEO Matt Schatzman said.

Work on Train 1 is progressing, with electrical, mechanical and utility commissioning under way. The gas inlet facilities also achieved ready-for-start-up status.

“We expect first LNG production from Train 1 in the second quarter of 2027, and substantial completion of Train 1 in the third quarter of 2027 – one quarter ahead of the guaranteed completion schedule under our EPC contract with Bechtel,” Schatzman said at NextDecade's third-quarter 2026 business update.

Margins expected to top $6/MMBtu

Introduction of first feedgas is imminent, as the developer seeks to fast track the start-up and commissioning process of Trains 1 through 5 at Rio Grande LNG. to take advantage of “very favourable” market conditions.

“Spot LNG prices remain strong due to the loss of supply from the Middle East.

“Based on current forward LNG and U.S. natural gas prices, we project volume-weighted average implied margins on uncontracted volumes from Train 1 start-up through the date of first commercial delivery under the Train 5 long-term SPAs, together with the approximately 175 TBtu we sold in the first quarter of this year, to average over $6 per MMBtu – more than $1 per MMBtu above our base case guidance,” Schatzman explained.

FERC approval for Trains 1-5 uprating

The permitting process is advancing alongside construction and pre-commissioning works. NextDecade received authorization from the U.S. Army Corps of Engineers for Train 6 in record time, envisaged to add a further 6.03 mtpa of liquefaction capacity.

The uprating of Trains 1-5 was approved separately by FERC, allowing NextDecade to expand capacity of Trains 1-5 from 27 mpta to approximately 30.15 mtpa. The proposed Train expansion, together with the uprating of the first five trains could take combined capacity of the first six trains to 36.18 mtpa.

During the third quarter, Rio Grande LNG achieved several construction milestones: The gas inlet facilities reached ready-for-start-up status, the Bay Runner pipeline entered service and dredging works for the terminal’s LNG berths were completed along with basin and channel deepening.

FID on Train 6 targeted in H2-2027

In November and December, the developer will focus on safely constructing the first five trains at Rio Grande LNG, advancing the development of Train 6 toward a positive final investment decision in the second half of 2027, the CEO said.

He underlined NextDecade’s pursuit to further expand its LNG export capability by beginning the permitting process for Trains 7 and 8 with the US Federal Energy Regulatory Commission. (November 2, 2026, Source: https://lngjournal.com/index.php/latest-news-mainmenu-47/item/117542-nextdecade-targets-first-gas-at-rio-grande-lng-before-year-end)